List of Major Projects
Completion | Project Name | Scope of Work | Client | Location | Licensor(s) |
---|---|---|---|---|---|
On-going | Bottom Upgrading Project at Esfahan Oil Refinery: - 91,300 BPSD RFCC Unit -51,500 BPSD RFCC Naphtha HDT Unit -24,100 BPSD LPG Merox Unit -27,000 Nm3/h Propylene Recovery Unit -105,000 Nm3/h Hydrogen Production Unit -Future Petrochemical Units | Basic Engineering Design Package Endorsement Detail Design & Engineering Procurement Engineering Services For 24,100 BPSD LPG Merox Unit 27,000 Nm3/h Propylene Recovery Unit | Oil Design and Construction Company (IRAN) | Esfahan (IRAN) | -UOP -Axens |
On-going | Abadan Oil Refinery Upgrading Project (Phase II) | Assisstance in Commissioning | Oil Design and Construction Company (IRAN) | Abadan (IRAN) | |
June 2022 | Clean Fuels Project at Shiraz Oil Refinery: 26,000 BPSD Distillate Hydrotreating Unit 5,000 BPSD Isomerization (+ Naphtha Splitter) Unit Hydrogen Production Unit Sulphur Recovery Complex Utilities and Offsite Facilities | Feasibility Study Arranging Grant of Proven Licenses Basic Engineering Design and Support Services for Detail Engineering EIA Report and Obtaining Governmental Permissions Modularization of Certain Process Units | Oil Design and Construction Company (IRAN) | SHIRAZ(IRAN) | Honeywell UOP Kinetics Technology Le Gaz Integral |
December 2020 | 110,000 BPSD Tabriz Oil Refinery Products Upgrading and Improving Refinery Profit Margin: Isomerization Unit Residue Hydrocracker Unit Lube Vacuum Distillation Unit Catalytic Dewaxing Unit Hydrogen Production Unit Sulphur Recovery Complex Utilities and Offsite Facilities | Bridging Work Until EPC Award: Complimentary Work on DFS Pre-FEED Work and Licensor’s Selection FEED Services Bankable EIA Report Services for International Finance Legal and Contractual Services | Oil Design and Construction Company (IRAN) | TABRIZ(IRAN) | Research Institute for Petroleum Industry Le Gaz Integral Innovative Cleantech Incorporated HollyChem TIPS RAS |
November 2020 | Power Plants Using Renewable Energies | Research and Development Detailed Feasibility Study FEED Package EPC Work Operation and Maintenance | Innovative Cleantech Incorporated (IRAN) | YAZD(IRAN) | NA |
June 2020 | Mobile Flare Capturing | Research and Development Detailed Feasibility Study FEED Package EPC Work Operation and Maintenance | Innovative Cleantech Incorporated (IRAN) | AHWAZ(IRAN) | Innovative Cleantech Incorporated |
June 2020 | CCR Pilot Plant and Basic Design of Demo Scale Unit | Integrated Management EPC Work | Amirkabir University Of Technology (IRAN) | TEHRAN(IRAN) | Innovative Cleantech Incorporated Amirkabir University of Technology |
June 2019 | Mobile Oil Treatment | Research and Development Detailed Feasibility Study FEED Package EPC Work Operation and Maintenance | Innovative Cleantech Incorporated (IRAN) | AHWAZ(IRAN) | Research Institute of Petroleum Industry Innovative Cleantech Incorporated |
December 2018 | New 2,160 BPSD LPG Treating Unit of Abadan Oil Refinery Upgrading Project | Detailed Engineering and Procurement Engineering Services | Consortium of ODCC (IRAN)/ SEI (CHINA) | ABADAN(IRAN) | Innovative Cleantech Incorporated |
June 2018 | Energy Saving in Catalytic Reforming Units of Tehran Oil Refinery | Detailed Feasibility Study and Basic Engineering | Oil Design and Construction Company (IRAN) | TEHRAN(IRAN) | Alfa Laval Heurtey Petrochem |
March 2018 | Development of Innovative Technology for Pre-cast Pile Production, Curing and Driving | Engineering and Technical Support | Arvand Maritime City (IRAN | ABADAN (IRAN) | Prime Petroleum Sweden |
March 2018 | New 2,160 BPSD LPG Treating Unit of Abadan Oil Refinery Upgrading Project | Grant of License and Basic Engineering | Consortium of ODCC (IRAN)/ SEI (CHINA) | ABADAN (IRAN) | Innovative Cleantech Incorporated |
December 2017 | Heavy Fuel Oil Upgrading to Light Transportation Fuels in Iraq | Preliminary Feasibility Study | Prime Petroleum Sweden (SWEDEN) | NASIRIAH (IRAQ) | ENI Axens Honeywell UOP KBR |
March 2017 | 110,000 BPSD Tabriz Oil Refinery Products Upgrading and Improving Refinery Profit Margin | Detailed Feasibility Study | SK Engineering and Construction (KOREA) | TABRIZ (IRAN) | ENI Axens Honeywell UOP KBR |
December 2016 | Abadan Oil Refinery Products Upgrading and Maintaining Refining Capacity at 360,000 BPSD | Complimentary Feasibility Study | National Iranian Oil Engineering and Construction Company (IRAN) | ABADAN(IRAN) | Axens Holdor Topsoe Technip |
October 2016 | Abadan Oil Refinery Products Upgrading and Maintaining Refining Capacity at 360,000 BPSD | Feasibility Study | National Iranian Oil Engineering and Construction Company (IRAN) | ABADAN (IRAN) | Axens Holdor Topsoe Technip |